How to handle Milestone based payment in Sub Contracts


Forum|alt.badge.img+9

How do we handle Milestone based payment in Sub Contracts?

Best answer by Tharindu Illangasinghe

FPayab wrote:
FPayab wrote:

How do we handle Milestone based payment in Sub Contracts?

Can Sub Contract Valuation Plan be used to create payment based on the completed work?

Hi ​@FPayab,

 

The Sub Contract Valuation is exactly used for this purpose.

You can create Manual Supplier Invoices for each Valaution and make Payments.

View original
Did this topic help you find an answer to your question?

Forum|alt.badge.img+9
  • Sidekick (Partner)
  • March 3, 2025
FPayab wrote:

How do we handle Milestone based payment in Sub Contracts?

Can Sub Contract Valuation Plan be used to create payment based on the completed work?


Tharindu Illangasinghe
Superhero (Partner)
Forum|alt.badge.img+15
FPayab wrote:
FPayab wrote:

How do we handle Milestone based payment in Sub Contracts?

Can Sub Contract Valuation Plan be used to create payment based on the completed work?

Hi ​@FPayab,

 

The Sub Contract Valuation is exactly used for this purpose.

You can create Manual Supplier Invoices for each Valaution and make Payments.


Forum|alt.badge.img+9
  • Sidekick (Partner)
  • June 9, 2025
Tharindu Illangasinghe wrote:
FPayab wrote:
FPayab wrote:

How do we handle Milestone based payment in Sub Contracts?

Can Sub Contract Valuation Plan be used to create payment based on the completed work?

Hi ​@FPayab,

 

The Sub Contract Valuation is exactly used for this purpose.

You can create Manual Supplier Invoices for each Valaution and make Payments.

Does this also mean that i can create a partial valuation for (example) 5 quantity from the total of 10 qty for the same Line/item when using Quantity Valuation Method?


Reply