We have one site that receives and manufactures on Monday - Thursday, but we ship Monday - Friday. We had to set the Manufacturing Calendar M - F so we could get Need Dates on Friday (all work center calendars M - Th).
We tried setting the site distribution calendar M - Th and set a delivery route on all customers for M - F but that didn’t work. All of our suppliers/customers are shared among multiple sites and our other sites do receive on Friday.
Not sure if this is something for supply chain matrix for site, but looks like you have to do all suppliers and supplier addresses individually with other mandatory fields like lead times we don’t care to set there.
Any ideas would be super helpful.