Demand from project for configured part (DOP)

  • September 18, 2024
  • 5 replies
  • 100 views

Forum|alt.badge.img+1

Hi all,

do we have any chance to create a demand and issue configured parts (DOP) from project?

Any workaround or tricks that can be shared as we receive this error message:

 

Thank you

KR

F

Best answer by MR10

I have created an idea for this; Create Configured Part Purchase Orders (also from Project) | IFS Community

View original
Did this topic help you find an answer to your question?

5 replies

Forum|alt.badge.img+10
  • Hero (Employee)
  • 208 replies
  • September 18, 2024

Hi;

Creating a Customer Order Line for the Configured Part with Supply Type = DOP, DOP Connection = Automatic DOP and then connect the Customer Order Line to a Project Activity.

Then release the Customer Order,

this would create a DOP Header connected to the Project,

Also if customer order connection is not needed, then

We can crease a DOP Header for the Configured Part and

Then Connect the DOP Header to the Project Activity via RMB option in the DOP Header and

Then Create DOP Structure and  Release it.


Forum|alt.badge.img+1
  • Author
  • Do Gooder (Customer)
  • 2 replies
  • September 19, 2024

thanks a lot. true, this is an option but I am right to say that even with your proposal I am not able to issue this DOP/shop order created part from stock to project, right?

still, the costs appear on project which is one step forward.


Forum|alt.badge.img+10
  • Hero (Employee)
  • 208 replies
  • September 19, 2024

Hope you are referring to the Topmost part, once the Shop Order is received, the part will be moved to stock and will be in the Project Inventory as the Transaction has the Project ID, activity sequence etc, In Inventory Parts in Stock you can move between projects and Standard Inventory using the provided move options.

Here the Quantity of the Configured Part in the Project Inventory (Already accounted for a Project, may be by receiving a Shop Order for this Part which is Connected to a Project, or via a Move Transaction to Project Inventory) can be moved to another Project or the Standard Inventory.

 

This is a Configured part in the Standard Inventory, so it can be moved to a Project.

 


Forum|alt.badge.img+1
  • Author
  • Do Gooder (Customer)
  • 2 replies
  • September 19, 2024

true, thank you. but still I cant issue this part which is on project stock as it is a configurable part:

 

 

 

 

 

 

 

 


Forum|alt.badge.img+12
  • Hero (Employee)
  • 124 replies
  • Answer
  • October 29, 2024

Reply