Multi-Line Reqs created in Project Navigator - Pre-Posting

  • April 26, 2022
  • 1 reply
  • 65 views

Forum|alt.badge.img+5

Can you have the pre-posting selected within the project navigator so that it is pulled into the req when the requisition is created.  Rather than having to assign every line the pre-posting individually - - a PO that will have 100 lines, this gets time consuming.

1 reply

Kasun Manuranga
Superhero (Employee)
Forum|alt.badge.img+17

Hi @emilyk8r ,

Do you want to copy all Pre posting setup in the Project to your PR line created from the Demand tab?

If that is the requirement then it is possible.

 

  1. I have a Project with following Pre posting

 

  1. Setup posting control for M113.
  1. Create a demand line.
  1. Create a PR and see for Pre posting.

 

Is this what you expected?

 

Regards,

Kasun