Hi, what is the effect of the utilization and % in group of the person ID in the Manufacturing Labor Class window on the available load of the Labor class in the advanced planning Board. 

 

Thanks.

 

This topic has been closed for replies.

5 replies

Saman K
Hero (Employee)
Forum|alt.badge.img+9
  • Hero (Employee)
  • 65 replies
  • December 20, 2021

Hi 

There is no effect. APB will not take that in to account. I quote here the tooltip.

Hope this helps

Saman

 


  • Author
  • Do Gooder (Customer)
  • 4 replies
  • December 20, 2021
Saman K wrote:

Hi 

There is no effect. APB will not take that in to account. I quote here the tooltip.

Hope this helps

Saman

 

thanks but what parameter is used on APB to modify the available load of the labor class


Saman K
Hero (Employee)
Forum|alt.badge.img+9
  • Hero (Employee)
  • 65 replies
  • January 6, 2022

Hi Adam,

I really do not get this // what parameter is used on APB to modify the available//. Could you elaborate more with an example?

Thanks and regards

Saman


  • Author
  • Do Gooder (Customer)
  • 4 replies
  • January 24, 2022

Hi Saman,

For example, if I want an ID Person to work half of the time on a Labor Class and the other half on another Labor Class. How to make her available load visible on APB ?

Thank's.


  • Author
  • Do Gooder (Customer)
  • 4 replies
  • March 4, 2022

Hey @Saman K , can you answer my question? Thank’s

 