Used Cost not updated for Sub Contract records

  • April 30, 2026
  • 2 replies
  • 23 views

Forum|alt.badge.img+2

Hello! Could you please advise how we can populate the used cost field for sub contract line items in project connections/ project forecast. For POs this field is populated when the receipt is recorded. But for sub-contracts it does not populate when the valuation is certified even though the certified amount gets removed from the committed cost figure. Appreciate any input on this. Thank you!

 

2 replies

desilvasachitha
Hero (Partner)
Forum|alt.badge.img+12

Hi ​@YPADINUSHI,
Please see below table that maps different business steps/events throughout the sub contract process and respective costs.
 

Step/Object

Event

Planned Cost

Planned Committed Cost

Committed Cost

Used Cost

Sub Contract Revision and Items

  • Select Report Planned Cost option
  • Activate revision
  • Update planned cost

xx

 

 

 

Call Off (Unreleased)

  • Enter call of values

 

xx

 

 

Call Off (Released)

  • Release call off
  • Receive application
  • Certify valuation
  • Amend committed cost

 

 

xx

 

Sub Contract Valuation
(Receive Application)

  • Receive application for payment
  • Certify valuation

 

 

 

xx

 
Hope this helps. 

Cheers!
Sachitha


desilvasachitha
Hero (Partner)
Forum|alt.badge.img+12

Hi ​@YPADINUSHI,

My apologies, I misunderstood the question. 

If “used cost” doesn’t appear in the Project connections/Project Monitoring pages upon certifying the valuation there could be one of several culprits at play. 

Did you check the relevant posting controls, especially SCV13 to make sure they are properly setup with correct validity periods including the Project Pre posting AC2.

Moreover, please check if the associated accounts with former Posting control has been correctly mapped to the correct cost element in you case “Project Cost” under the “Cost Revenue element per code part value” page. 

You can trigger a “Project Connection Refresh Run” if any posting or cost element values have been recently changed which could be holding the used cost value in a transitionary state. 

Let me know how it goes