When a Tool/Equipment object is used on a Project Activity.

What is the best screen for recording those Hours on a Tool/Equipment object for a Project Activity ?

Hi @AntonioInfoConsulting,

So far I know we only have an option to do so on Work Orders / Work Tasks.

In case you need these hours also on your project, you need to create a Work Order from a project activity and report the tool hours on that work order (Work Task from IFS10).

It would be a good idea to have the option to report tools directly on thr project, you can create an idea for this in this community.

Good luck,

Robert

 


I agree, when one are able to plan an resource, but not use it in project it is only half ready as a product.  We are implementing Resource management at customer from Service and Project perspective, and this flaw is huge for the solution.