Forum|alt.badge.img+12

I have a Manufactured Inventory Part in Project Deliverables and have the Max Lot Size set to 1.  Within PD, the Material Plan shows that I have only 1 shop order.  If I have Max Lot Size set to 1, shouldn’t I have multiple shop orders?

Am I doing something wrong?

Patrick

Best answer by Yathartha Karunananda

Hi ​@PIreland,

Max Lot size is used for MRP planning and it will not be considered in project deliverables when material plan generation.


~Mark this as the best answer if it solves your issue~

1 reply

Yathartha Karunananda
Hero (Employee)
Forum|alt.badge.img+11

Hi ​@PIreland,

Max Lot size is used for MRP planning and it will not be considered in project deliverables when material plan generation.