When exporting a project from IFS to MS Project, the lag time converts to hours from days (even though the schedule in MS Projects is set to days. Any help would me much appreciated.

Forum|alt.badge.img+4
  • Sidekick (Employee)
  • May 10, 2022

Lag time in IFS is only set in hours, so a recalculation is required!