Project Budget Control Summary has no records


SMANUEL
Sidekick (Partner)
Forum|alt.badge.img+9
  • Sidekick (Partner)
  • 53 replies

Project Budget Control Summary has no records for certain Projects..

What could be the reason ?

Thanks in Advance

 

Best answer by Brijesh410

its manual controls created by user. you can do it both ways, control as budgeted will create rules automatically.

View original
Did this topic help you find an answer to your question?

6 replies

Forum|alt.badge.img+4
  • Sidekick (Partner)
  • 16 replies
  • May 18, 2022

Hi Shibu Manuel,

 

Budget Control Rules can be enabled in multiple ways:

  • Control On Total Budget
  • Control As budget

If Project is Enabled with “Control On Total Budget”, Project Budget Control Summary screen will have only header information with Total Budget and Total Consumption.

 

Whereas, If Project is Enabled with “Control As Budget”, Project Budget Control Summary screen will have line details with Subproject, Activity,……..

 

In your attached screen also, “Control On Total Budget” is selected. Please check.

 

Hope this clears your query. :)

 

/Ram


SMANUEL
Sidekick (Partner)
Forum|alt.badge.img+9
  • Author
  • Sidekick (Partner)
  • 53 replies
  • May 19, 2022

Hi Ram,

Thank you for your response..

Here is another project for instance,having “Control On Total Budget”  selected and show the records!

 


Forum|alt.badge.img+4
  • Sidekick (Partner)
  • 16 replies
  • May 19, 2022
SMANUEL wrote:

Hi Ram,

Thank you for your response..

Here is another project for instance,having “Control On Total Budget”  selected and show the records!

 

Hi Shibu Manuel,

In this case, Project is enabled with both ‘Control As Budgeted’ and ‘Control On Total budget’.

Please check the Budgeting and Forecasting Indicators for the respective project, it will be enabled with both options.

Thanks.

 

/Ram


SMANUEL
Sidekick (Partner)
Forum|alt.badge.img+9
  • Author
  • Sidekick (Partner)
  • 53 replies
  • May 22, 2022

Hi Ram,

Infact both the options are not enabled on this particular Project..

Control on Total budget is checked..

 


Forum|alt.badge.img+6
  • Sidekick
  • 17 replies
  • Answer
  • August 20, 2022

its manual controls created by user. you can do it both ways, control as budgeted will create rules automatically.


SMANUEL
Sidekick (Partner)
Forum|alt.badge.img+9
  • Author
  • Sidekick (Partner)
  • 53 replies
  • August 21, 2022

@Brijesh410 Many Thanks for the response


Reply