Hi,
I have Project Misc Demand on an Activity, which I used to create and receive material in against a PO. Now I have material within the Project Inventory.
I created a Work Order & Work Task connected to this activity. I then created a Material Req on the Work Task (Supply Code Project Inv) and reserved and issued the part on the Work Task.
I was expecting the Project Misc Demand to also show a quantity issued of 1 but it’s still showing in Project Misc Demand Issued Quantity of 0.
Is this expected behaviour? Do I need to manually (or automate) the issuing of project misc demand, even if it’s been issued on a connected work task?
Thank you