Can't change early finish date of an Activity

  • January 17, 2022
  • 4 replies
  • 327 views

SMANUEL
Sidekick (Partner)
Forum|alt.badge.img+9
  • Sidekick (Partner)
  • 57 replies

can't change early finish date of an Activity, although we had modified the required dates on all the existing demands to be in line with the desired finish date

 

 

Best answer by Dilan Senevirathne

Hi @SMANUEL 

If the required dates of all the demand lines are within the Early Start & Finish dates, I believe this issue needs in depth investigation. Hence creating a ticket to IFS support is the best solution I can think of.

Best Regards,
Tharaka.

4 replies

Dilan Senevirathne
Superhero (Partner)
Forum|alt.badge.img+14

Hi @SMANUEL 

Can you provide  a screen shot of the “Demand” tab. Make sure you capture the “Required Date” field

Best Regards,
Tharaka.


SMANUEL
Sidekick (Partner)
Forum|alt.badge.img+9
  • Author
  • Sidekick (Partner)
  • 57 replies
  • January 23, 2022

@Tharaka Senevirathne Thank You for the response..

Earlier we had modified the Required dates of all the existing demands on this particular Activity, to be within the Early Start & Finish dates..

To our surprise, we were able to change the dates the very next day!!

Thanks Much


Dilan Senevirathne
Superhero (Partner)
Forum|alt.badge.img+14
  • Superhero (Partner)
  • 134 replies
  • Answer
  • January 23, 2022

Hi @SMANUEL 

If the required dates of all the demand lines are within the Early Start & Finish dates, I believe this issue needs in depth investigation. Hence creating a ticket to IFS support is the best solution I can think of.

Best Regards,
Tharaka.


SMANUEL
Sidekick (Partner)
Forum|alt.badge.img+9
  • Author
  • Sidekick (Partner)
  • 57 replies
  • January 23, 2022

@Tharaka Senevirathne will do that next time ..Thanks Much