Issue Description : Activity Details Disappear After opening the Project Scope and schedule
Steps to recreate the issue
1. Navigate to Project Management >Plan and Execute> Activity - Activity Details - Dropdown option is available for Setup Parameters, Material and Services, Resource Planning and Monitoring

2. Navigate to Project Management > Plan and Execute > Project Definition - From project details go to Scope and schedule

3 Activity Scope and Schedule > select Activity

4. Now Navigate to Project Management >Plan and Execute> Activity - Activity Details is not available.