Setting up planning structure from product family master
Best answer by Saneeka Wijesinghe
“Structure line items of the plan structure belong to the one and only top-level family. Each line item identifies either a subfamily or a Level 1 master-scheduled part.”
These parts can be manufactured in one site or different sites. Though these are manufactured in different sites these parts are planned under the same product family.
“The Quantity per Assembly field should typically hold a value between 0 and 1. This indicates the percentage that the subfamily or part constitutes of the parent family. “
When the total exceeds 1, a warning message is displayed but can still commit the data selecting Yes. Disaggregation and aggregation will use this QPA values for the calculation. So these values we get from those calculations will affect.