Phase out Structure Alternate*

  • 17 January 2023
  • 1 reply
  • 70 views

Userlevel 1
Badge +5

Hello,

 

How do you make another structure the default one? Is the only way marking is as “*”?

How can we phase out the *Alternate?

 

Thanks for any input,

Alina

icon

Best answer by Björn Hultgren 17 January 2023, 18:38

View original

1 reply

Userlevel 7
Badge +23

Alternate * is always the default. Phase In and Phase Out dates are not controlled by the Alternate itself but the Part Revision. So if you want to phase in a new alternate from a certain date you must create a new revision. 

Reply