How to prevent starting the next operation

  • December 7, 2021
  • 1 reply
  • 132 views

Forum|alt.badge.img+11

Hi,

 

In my shop order, how can I prevent that an operation can be started before  the previous operation was reported?

 

Using date is not enough, as they are to variable in this case.

 

I want that operation N+1 can only be started if operation N has been reported.

 

Thanks!

Best answer by Björn Hultgren

You can select the Milestone Operation option. This enforces that enough quantity has been reported on the previous operation. 

 

This topic has been closed for replies.

1 reply

Björn Hultgren
Hero (Employee)
Forum|alt.badge.img+25
  • Hero (Employee)
  • 1061 replies
  • Answer
  • December 7, 2021

You can select the Milestone Operation option. This enforces that enough quantity has been reported on the previous operation.