Skip to main content
Solved

How to connect a change order to a Parked shop order ?


Forum|alt.badge.img+8

Dear Community,


We are currently figuring out the best way to use the possibility of parking a shop order.

Does someone know how to connect a change order to a parked shop order ? When clicking on the drop-down menu of change order no, there is no data whereas we have change orders in the table.

 

 

Thanks for your help ðŸ˜Š

 

Best answer by Björn Hultgren

@Carole To connect a Change Order when parking a shop order, I believe it must have an action that is connected to either:

  • The shop order
  • An operation on the shop order
  • The shop order part 
  • A component part of any material line on the shop order

I made a quick test and connected the change order action to part = PTS

Then this change order appears in the loV in the Part Shop Order dialog for shop orders that are using this component

 

View original

Forum|alt.badge.img+8
  • Sidekick (Customer)
  • May 14, 2024

We have also the same sort of situation when trying to connect a MRB case ðŸ˜•


Björn Hultgren
Hero (Employee)
Forum|alt.badge.img+24

@Carole To connect a Change Order when parking a shop order, I believe it must have an action that is connected to either:

  • The shop order
  • An operation on the shop order
  • The shop order part 
  • A component part of any material line on the shop order

I made a quick test and connected the change order action to part = PTS

Then this change order appears in the loV in the Part Shop Order dialog for shop orders that are using this component

 


Forum|alt.badge.img+8
  • Sidekick (Customer)
  • May 15, 2024

@Björn Hultgren 

It is perfect ! Thanks you so much for your help


Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings