Solved

Different date is displayed in “MS for Multiple Parts" instead of the finish date in Shop Order

  • 27 January 2022
  • 1 reply
  • 59 views

Userlevel 3
Badge +3

We have observed in "MS for Multiple Parts" screen, Period Day of the “lot size” is set to Finish Date (of Shop Order) + 1 working day.

 

Lot size of Shop Order is displayed in "Work in Process" line in "MS for Multiple Parts" screen and the date of the lot size is displayed in column header.

Is it possible to display the Finish Date of Shop Order in "MS for Multiple Parts" screen as well?

Regardless of Schedule Direction (whether "Manual Scheduling" or "Backward Scheduling") the Lot Size of Shop Order is displayed in the Finish Date + 1 Day column on the "MS for Multiple Parts" screen.

icon

Best answer by Björn Hultgren 27 January 2022, 10:20

View original

This topic has been closed for comments

1 reply

Userlevel 7
Badge +23

The supply coming from a shop order is considered available the workday after the shop order finish date. It is the same if you look in Inventory Part Availability Planning, the Due Date of a shop order supply appears on the day after its finish date.

in IFS Cloud 21R2 the “Intraday Planning” concept was introduced, if a manufactured part is setup for intraday planning the supply will appear the same day as the shop order is finished. This is more described in this YouTube video.