Is CRP run in parallel or before MRP is run? After running the CRP functionality, which windows can be used to view the results?

icon

Best answer by Björn Hultgren 15 November 2021, 12:42

View original

This topic has been closed for comments

1 reply

Userlevel 7
Badge +23

CRP is typically run after MRP to create load for the shop order requisitions generated by MRP. MRP can however be setup to run integrated with CRP which allows material demand to be planned by operation start dates rather than shop order start date.

In IFS cloud you can you Visual Capacity Requirements planning to analyze the CRP result per time period and work center and labor class using charts. In Enterprise Exlorer you can use Machine Load per Work Center and Labor Load per Labor Class windows and then use the visualizer mode to show charts.

The outcome of the CRP in its most detailed form can be viewed in Machine Load Details and Labor Load Details pages.