Hi,
We are trying to automate our planners tasks for the start of the day and to use a task chain for the repeatable actions:
- calc ms lev 1
- run mrp
- automatic shop order processing
This runs but we don't get any requisitions created for the current day. When we re-run MRP manually we get the SO requisitions as expected. We are on Apps 8 (moving to Cloud) and have spread the tasks out so they don't overlap and run at the same time.
We are not sure why auto vs manual running would result in a different result - any ideas?
Thanks for any help and considering,
Regards,