Good afternoon,

We are struggle with APB, following a nice user guide, we try to take our hands on it but we face a technical issue at point 2.2.6.

First, after loading shop order, is it not colored as in the manual:

Example from the manual

 

what i observe:

 

when i RMB Scheduling: SO remain unscheduled.

Someone could help me to start?

 

Hi,

There may be many reasons why APB is unable to schedule and often it is data related.

Some things to try …

Expand the Shop Order to show the Operations

 

Double left click on the Operations to see more details. In my example, I don’t have a resource associated with the Labour Class so APB is unable to schedule.

 

This can then be corrected here 

 

 

Reload the data into APB. 

 

The Shop Order Operations are now scheduled (infinitely scheduled)

 

Select RMB option ‘Scheduling’

 

Press OK

 

In my example, the operations are now finitely scheduled and tardy (does not meet the Need Date)

 

 

I hope that this helps.