PM Action maintenance plan not generating 24R2

  • September 29, 2026
  • 5 replies
  • 58 views

Forum|alt.badge.img+13

All, can anyone tell me why this PM Action is not generating a maintenance plan even when I manually click generate plan. The user needs to see these dates in a plan for our auditors.

PM Action is active

PM Action is set to generatable

PM Action is connected to Calendar 01-MAINT

Maintenance Trigger is set to following:

Start Unit - Day

Start Date - 23/09/2028

Interval unit - Year

Interval - 2

Current limit of plan is 2031

01-Maint Calendar is generated and end date is 31/12/2031

 

Best answer by sholmes

We have finally found the reason - the Calendar associated with the Maint Org in basic data was different - once this was changed to be the same as the one in the PM Action the plan generated as expected. The calendar that was against the Maint Org was only generated to 31/12/2027.

5 replies

Forum|alt.badge.img+4
  • Sidekick (Partner)
  • September 29, 2026

Have  you extended the maintenance plan, it is recommended to  extend for one to two  years at a time. Look for extend maintenance plan,


Forum|alt.badge.img+13
  • Author
  • Hero (Customer)
  • September 29, 2026

​@jorlin - as you can see from the screen shot on the extend/shorten plan page it current year limit is 2031 - is there somewhere else that you set this?


Forum|alt.badge.img+11
  • Hero (Employee)
  • September 29, 2026

Where is this env?
I believe there was some issue with Oracle 19.28 at least.
Oracle 19.32 fixed it, but will then require grants in order to install deliveries in remote.


Forum|alt.badge.img+4
  • Sidekick (Partner)
  • September 30, 2026

​@jorlin - as you can see from the screen shot on the extend/shorten plan page it current year limit is 2031 - is there somewhere else that you set this?

Nope, this is the place i was mentioned to. Have you tried to generate wo from the maintenance plan on a individual PM Action?


Forum|alt.badge.img+13
  • Author
  • Hero (Customer)
  • Answer
  • October 7, 2026

We have finally found the reason - the Calendar associated with the Maint Org in basic data was different - once this was changed to be the same as the one in the PM Action the plan generated as expected. The calendar that was against the Maint Org was only generated to 31/12/2027.