When using condition based PM Action, is there a way to reduce the forecast calculation that is auto started when a measurement is entered? It’s currently looking like it goes out 2 years, or over 1000 lines and this is impacting the saving of the measurement.

Any suggestions on how to improve this are very much appreciated as we just starting to use this part of the software

IFS Cloud 24R2

Thanks in advance, Sarah

Hi ​@sholmes 

Please check the value you have for object property PM_PLAN_HORIZON ?

Best Regards,

Thilini


Hi ​@sholmes ,

You can change the object property below to 'BATCH' if it is currently set to 'ONLINE'. This will reduce the time it takes to save measurements, and the calculation of maintenance plans will occur in the background.
 

Thanks,