Have you ever encountered a situation where you had to manage the relationship between an inventory part with inventory expiration tracking and MRP usage?
In other words, there is an inventory part and it has an expiration date. In the standard structure, the system manages the supply process by considering the expiration date into account during the MRP calculation.
However, in the MRP calculation logic, it is requested to make MRP calculations by ignoring the expiration date, is this request possible?
Could you share your experiences and knowledge?

 

Thanks

Ozge

Best answer by Abdul

Hi ​@Ozge,

Mandatory Expiration Date flag on the Inventory Part screen controls whether MRP and Master Scheduling will consider the expiration date when calculating the required supplies.

 

Regards

Abdul Rehman

1 reply

Abdul
Superhero (Partner)
Forum|alt.badge.img+20
  • Superhero (Partner)
  • Answer
  • April 21, 2025

Hi ​@Ozge,

Mandatory Expiration Date flag on the Inventory Part screen controls whether MRP and Master Scheduling will consider the expiration date when calculating the required supplies.

 

Regards