Hi,
I have an issue with the creation of purchase requisitions. Some requisitions are automatically created with “latest order date” in the past.
It seems like it sabstracts the Supplier Manufacturing Lead Time as weekdays (5) and not calendar days (7).
For a part #7513, the supplier manufacturing lead time is 10 days.
For this supplier, the external transport, the transport, the internal transport and safety lead times are 0.
So the “latest order date” should be equal to : Wanted receipt date - Supplier Manufacturing Lead time.
But, a purchase requisition line was created with “wanted receipt date = 08/04/2026” and “latest order date = 20/03/2026”
Am I missing something ?