Skip to main content
Question

IFS Cloud 26R1 – Planned Delivery Date for Customer Orders when Wanted Delivery Date is in the Past

  • Nov 13, 2026 2:55 AM UTC
  • 3 replies
  • 79 views

Forum|alt.badge.img+2

Hi everyone,
I would like to understand how IFS Cloud 26R1 calculates the Planned Delivery Date for a Customer Order when the Wanted Delivery Date is in the past.


Does IFS automatically adjust the Planned Delivery Date to the current date or order creation date when the requested delivery date has already passed?
Is this standard system behavior for Customer Orders, or does it depend on specific lead-time settings, calendars, supply codes, or other configurations?


Could anyone explain which configuration or calculation controls this behavior?
Thank you for your help!

3 replies

Forum|alt.badge.img+6

Hi Suzukih,

In IFS Cloud 26R1, the Planned Delivery Date is calculated based on the Wanted Delivery Date and the applicable supply lead times.

If the Wanted Delivery Date is in the past, IFS performs a backward lead-time calculation, which may result in supply dates that are also in the past.

IFS does not necessarily move the Planned Delivery Date to today's date or the Customer Order creation date automatically.

The calculation also depends on the Supply Code, inventory availability, lead-time settings, and applicable calendars.

The documented baseline is:

Wanted Delivery Date → Backward Lead-Time Calculation → Supply Availability Check → Delivery Feasibility.

Hope this clarifies!


Michael Kaiser
Hero (Customer)
Forum|alt.badge.img+10

Hi,
just want to add an idea realised in our FACT_CustomerOrderLines:

,CASE 
-- WHEN CO.ROWSTATE IN ('Released','Reserved','PartiallyDelivered','Delivered','Blocked','Picked','Invoiced',Partially Invoiced')
 WHEN CO.ROWSTATE NOT IN ('Planned','Cancelled')
 AND  COL.ROWSTATE NOT IN ('Cancelled','Blocked') --,'Invoiced')
-- THEN COL.PLANNED_SHIP_DATE                                                        
THEN isnull(cast(ITH.ActualShipDate AS date),isnull(cast(ITH.MaxPlannedShipmentDateSP as date),isnull(COL.PLANNED_SHIP_DATE, 
-- CAST(getdate() +90 as date))))                                                    -
   cast((CAST((year(getdate()) +2) as varchar)) + '-12-31' as date))))

-- 13.06.22 fallback angepasst.
 --ELSE CAST(getdate()+90 as date)
 ELSE cast((CAST((year(getdate()) +2) as varchar)) + '-12-31' as date)
 END                                                                                as ExpectedInvoiceDate

Because we add COL and CIL into a FACT_Sales we have the “real” InvoiceDate and a “fake” InvoiceDate from the COL (if not yet invoiced).
So we can have a “look into the future”. 

BR
Michael


Forum|alt.badge.img+2
  • Do Gooder
  • Nov 23, 2026 11:27 AM UTC

Hi Suzukih,

The Planned Delivery Date is initially set to the Wanted Delivery Date in IFS Cloud 26R1. However, the system then performs date calculations to determine whether the requested delivery date is achievable.

The calculation depends on several factors, including:

Supply Code: Determines which lead times are considered (Inventory Order, Shop Order, Purchase Order, etc.).

Lead Times: Picking lead time, external transport lead time, manufacturing lead time, and other applicable parameters.

Calendars and Routes: Distribution, transportation, and customer calendars can affect the calculated dates.

Availability Check: If enabled, the system evaluates whether the required quantity can be supplied by the requested date.

If the Wanted Delivery Date is already in the past, the system may calculate a later Planned Delivery Date when availability checking or rescheduling determines that the original date cannot be met.

However, I would not expect the Planned Delivery Date to be automatically replaced with the current date or order creation date in every scenario simply because the Wanted Delivery Date has passed.

I would recommend checking the Supply Code, Availability setting, applicable lead times, and whether any availability checking or replanning functionality is being triggered.

Hope this helps!