Changing Visual Shop Order Operations Planning

  • Nov 11, 2026 2:57 PM UTC
  • 1 reply
  • 26 views

When using Visual Shop Order Operations Planning it shows the work centers with their available hours per workday, I am wondering if it is possible to change this screen to work off total quantity per day as we use that over hours in some areas for scheduling. If that is not possible is there a screen in IFS where we can get a visual to quantity to ensure nothing is overbooked. We are on IFS cloud. 

1 reply

Forum|alt.badge.img+6
  • Do Gooder (Partner)
  • Nov 24, 2026 5:28 PM UTC

Short answer: I would not try to bend Visual Shop Order Operations Planning onto quantity. That page is the Gantt style schedule of operations (the Machine Operations Scheduling and Labor Operations Scheduling charts), and its colouring of each resource and day is load against calculated capacity. For a view that shows whether anything is overbooked, use the load charts on Visual Capacity Requirements Planning, and if your real limit is units per day rather than hours, Resource Requirements Planning is the screen built to hold capacity in any unit of measure.

Why the page shows hours

Capacity for a work centre is calculated from its calendar, its utilisation and the resource efficiency and validity periods, by the Calculate Work Center Resource Capacity for Manufacturing run. The operations page then colours each resource and day as Not Loaded, Partially Loaded, Fully Loaded, Overloaded, No Capacity Load or Past Due by comparing the operation load with that capacity. So the hours you see are a property of how capacity and load are held, not a display option on the chart.

A setup along these lines for seeing overbooking

  • Keep capacity current: run Calculate Work Center Resource Capacity for the site, for example out to the end of your planning horizon, and schedule it as a task so it does not go stale. Check the result on the Capacity tab of the Work Center page.
  • Open Visual Capacity Requirements Planning (Supply Chain Planning, Capacity Requirement Planning). Click the magnifying glass and search either for your shop orders or for the work centres and the time period.
  • Use the Machine Load chart: load is bars per day or per week and capacity is a line, so a bar above the line is an overbooked day. For example set Aggregate By = Day, Group By = Operation with Color By by order, Load Dates = Search Interval so empty days show, and Capacity Type to match whether you want work centre utilisation applied.
  • Add Machine Availability Summary for the quick view of which work centres, departments or production lines are Overloaded on at least one day.
  • To fix a problem from the chart, select the segment for the order or operation and use Schedule Shop Order or Schedule Operation Block, then go back to Operations Planning to sequence the operations.
  • If you prefer a list to a chart, the load pages (for example Machine Load per Work Center and Load and Capacity per Work Day) give the same load by work day, and Shop Order Operations has a command that opens Machine Load per Work Center for the selected work centres.

If your limit really is quantity per day

  • Resource Requirements Planning (Supply Chain Planning, Resource Requirements Planning) holds capacity in any unit of measure, not only hours. You define a capacity scenario, connect it to the work centre on the RRP Capacity tab, and on the Capacities tab enter Units per Day, Efficiency and Calendar. A work centre in kg or pieces per day is a normal setup, and each scenario has a Load Source and an Overload/Underload Threshold.
  • The results are on RRP Load Analysis, RRP Load Details and RRP Load per Work Centers, where load and capacity are compared in your own unit.

The awkward case

Resource Requirements Planning is a mid to long term view driven by the master schedule or the sales and operations plan, and it plans on shop calendar working days only. Orders that are created directly on the shop floor and never pass through that plan will not appear as RRP load, so check whether your scheduled work flows from the master schedule before you rely on it day to day.

Things to know

  • The load charts only fill after you search with the magnifying glass, and what counts as load depends on the Load Source setting, so an overload can disappear if a load type is switched off.
  • Capacity is only as good as the last capacity calculation. If the line looks wrong, rerun it before changing anything else.
  • The Operations Planning Gantt shows the operations on the work centres of what you searched, plus a day either side, so it suits sequencing rather than totals.

Worth a look: the IFS Cloud documentation for Analyze Machine Load Chart, Analyze Machine Operations Scheduling Chart, Calculate Work Center Resource Capacity for Manufacturing and About Resource Requirements Planning.

Is the quantity limit a physical one per work centre (an oven, a batch size) or a planning rate you apply across several work centres? That decides whether Resource Requirements Planning is the better fit.

Created with the help of Ask Olive.