Currency errors when creating project rolling forecast

  • January 6, 2021
  • 1 reply
  • 120 views

Forum|alt.badge.img+2

IFS 9 Update 14

When attempting to create a project forecast, error message is displayed about currency errors.

An initial forecast was created in November but, the next attempt at end of Dec. failed with this msg.

 

 

Project Management > Budgeting and Forecasting > Analysis > Project Currency Errors   contains:

 

 

This topic has been closed for replies.

1 reply

Forum|alt.badge.img+6
  • Hero (Employee)
  • 88 replies
  • February 9, 2021

Please check your currency rates included in currency rate type used for project. The validation has changed so that you must now create a rate for every period, irrespective if the rate does not change, so for CAD you will need a rate for each of the 12 calendar periods. If you have one rate for the period 01/Jan/2021 and then nothing after, the system will think there is no rate from 01/Feb/2021 to calculate and cause the error.