PSO Start/End Shift

  • Feb 21, 2024 8:46 PM UTC
  • 3 replies
  • 109 views

rfedorchuk
Sidekick (Customer)
Forum|alt.badge.img+7

Hi All,

We’re trying to figure out what the data source for this is in PSO:

 

If I make changes to this in Scheduling Resources, it doesn’t seem to have an effect on the shift start/end

 

I have tried sending the changes to the dataset, but that didn’t seem to change anything.

 

Thanks,

Rob

Best answer by Alexander Heinze

After making changes to the Scheduling Resource’s location, did you re-generate the shifts and send a Full Load to PSO?

View original

3 replies

Alexander Heinze
Ultimate Hero (Employee)
Forum|alt.badge.img+25
  • Ultimate Hero (Employee)
  • Answer
  • Feb 22, 2024 7:54 AM UTC

After making changes to the Scheduling Resource’s location, did you re-generate the shifts and send a Full Load to PSO?


rfedorchuk
Sidekick (Customer)
Forum|alt.badge.img+7
  • Author
  • Sidekick (Customer)
  • Feb 22, 2024 2:45 PM UTC

Why would I have to send a full load?  This seems like a huge hit on our database.

I will try it and update.


rfedorchuk
Sidekick (Customer)
Forum|alt.badge.img+7
  • Author
  • Sidekick (Customer)
  • Feb 22, 2024 2:59 PM UTC

So, sending changes did not work.

Sending full load did.

Any idea why sending changes would not work?