Hi All,

We’re trying to figure out what the data source for this is in PSO:

 

If I make changes to this in Scheduling Resources, it doesn’t seem to have an effect on the shift start/end

 

I have tried sending the changes to the dataset, but that didn’t seem to change anything.

 

Thanks,

Rob

After making changes to the Scheduling Resource’s location, did you re-generate the shifts and send a Full Load to PSO?


Why would I have to send a full load?  This seems like a huge hit on our database.

I will try it and update.


So, sending changes did not work.

Sending full load did.

Any idea why sending changes would not work?