We are currently having this issue in PSO. We created several regions and connected for the beginning three resources to the regions. However, they are shown as duplicates on the gantt. In this case, resources 457, 464 and 494 are shown above, as if they wouldn’t belong to any regions and also under the current region. We deleted the resources, created them again, as usually, but nothing worked until now. Do you have any ideas here?

 

Thank you,

Iulia

Can you have a look (or share screenshots) of the load message in PSO? Specifically Region and Resource Region, and if applicable Resource Region Availabilities.


Hello ​@Alexander Heinze, of course.

 


When you see a resource in the tree AND outside the tree, it usually means that (using Valid From/To or Availabilities) the resource has a period in which it doesn’t belong to any region. Have just replicated that. If you don’t have availability patterns, try to set Valid From and Valid To outside your scheduling horizon (e.g., 2024-2026).


Hi ​@Alexander Heinze, amazing, it worked. As always, thank you very much.


Reply