WHAT'’S IS THE DIFFERENT BETWEEN WORK TASK AND WORK TASK STEPS IN IFS 10?

WHAT'S TIME REPORT IN IFS 10?

 

Hi Patrick,

  • Work task is the planning object for a planned period of work for one or more persons, which is linked to a single work order. It defines the demands (resource, material etc.) to fulfil the requirement, collects cost and generates revenue. The activities are defined as task steps.
  • Work Task Steps are the details of steps that are required to perform a work task. The work task step is not a sub task, and the difference is that it is not possible to add demands (resources, materials etc) on a step line or to create transactions (time, issues etc.) directly to a step.
  • You can report the amount of time spent on a specific job and who did it in time reporting. I.e. reporting of actual costs which is done by reporting hours for Employees and Tools.

Hope this helps.

 

Best Regards,

Yasanthi