On Work Task > Allocate Resource there is a field “Adjust to Schedule”
My team is asking if this can be defaulted to be checked.
Is there an easy way to do this?


On Work Task > Allocate Resource there is a field “Adjust to Schedule”
My team is asking if this can be defaulted to be checked.
Is there an easy way to do this?


Best answer by JONHSE
I have not checked in APP10, but in CLOUD:
Set the flag ‘Allow Multiple Visits’ to TRUE. You can set it on individual Work Tasks or set it by default on Site.
If the Work Task has ‘Allow Multiple Visits’ = TRUE then ‘Adjust to Schedule’= TRUE