Information about Print Requisition, when a Purchase Requisition is in “Closed” and “Planned” Status The RMB function for Print Requisition is not available, However when a Purchase Requisition is in “Released”, “Partially Authorized” and “Authorized” Status the RMB functionality is available for Print Requisition
Is this Standard behaviour?
what's the logic if Standard behaviour
Hope someone can assist me
Regards
Mona
Best answer by RigsIrosh
I believe the requirement of printing the Purchase Requisition is there when the internal demand exists within the procurement dept.
At initial stage (planned stage) the demand is not released for further evaluation and once the PR is converted to Quotation or Purchase Order then the actual demand line is transferred to next level where there is no longer requirement to print the PR.
I know this is not documented anywhere but just sharing the experience!
I believe the requirement of printing the Purchase Requisition is there when the internal demand exists within the procurement dept.
At initial stage (planned stage) the demand is not released for further evaluation and once the PR is converted to Quotation or Purchase Order then the actual demand line is transferred to next level where there is no longer requirement to print the PR.
I know this is not documented anywhere but just sharing the experience!