Manufacturing lead time

  • 17 June 2021
  • 3 replies
  • 249 views

Userlevel 5
Badge +9

Hi 

does any one know if there is a way on IFS apps 10 to which displays the complete manufacturing ONLY lead time for a top level part which includes all the lower level parts that are consumed by top level structure? 

regards

Jamie 

icon

Best answer by Jagath Dharmakeethi 21 June 2021, 19:09

View original

This topic has been closed for comments

3 replies

Userlevel 6
Badge +20

Are you looking for a cumulative lead time calculation that would omit all purchase part lead times? Maybe possible through a custom menu item to perform the calculation into a  custom field.

Userlevel 5
Badge +9

Hi Matt

not after cumulative lead time but only manufactured lead time of the product structure across all levels?

 

Userlevel 4
Badge +7

Hi Jamie,

 

I don’t see any specific field which can fulfill your requirement.

 

However, I have 2 suggestions.

Please check attached