Skip to main content
Solved

cancel purchase change order in apps 10 when connected to project activities

  • April 1, 2026
  • 1 reply
  • 40 views

Forum|alt.badge.img+2

When we go into the Change order line 2 has been cancelled but it has been linked to Activities and when we try to update the Purchase order we get this message. We have tried lots of options to cancel the change order but it’s just stuck.

We just want to cancel the change order and Cancel the 2nd line on the purchase order

 

Best answer by Lingesan08

Hi ​@aathomascommunity ,

     The PO line is linked to a Project Activity that is not in Planned or Released status. IFS only allows removing project connections in those statuses.

     You need to revert the activity to Released/Planned (if possible) or remove the project connection first. Otherwise, cancellation of the change order/PO line will not be allowed.

1 reply

  • Answer
  • April 1, 2026

Hi ​@aathomascommunity ,

     The PO line is linked to a Project Activity that is not in Planned or Released status. IFS only allows removing project connections in those statuses.

     You need to revert the activity to Released/Planned (if possible) or remove the project connection first. Otherwise, cancellation of the change order/PO line will not be allowed.