Hi All,
Is it possible to add multiple Project IDs to different PO lines through Project connections?
Currently, system is not allowing to add different Project ID to different PO lines.
We have to raise a separate PO for each Project ID connected PO lines.
Getting the below error while trying to add the multiple project Id.
So kindly suggest.
Thanks in advance.
Page 1 / 1
Hi @ProShiraA
Probably the projects are set to ‘Project Unique Billing’, if you uncheck these, it should be possible to have one PO with multiple lines connected to dffernt projects.
Hope this will help,
Robert
Hi
Shiraj,
you can check the fields on the project. If this check box is selected, you may be getting error.
Hello @EqeRobertK, @ProShiraA, @KEVSER
I tried disabling the box for “project unique procurement” and it seems like I can’t do it if the project is approved or started.
I get the following error msg :
I tried the modification when projects are initialized or completed and no error msg stops me from saving.
I was wondering if you faced the same issue, if yes, is there a way to modify it on already approved/ started projects?