Hi Community

How can i manage One Workorder with multiple Asset

This fonctionnality exists in other CMMS solution (MAXIOn,..) but not in IFS. How can i manage this issue

Thans for your help

icon

Best answer by Thommy 8 October 2021, 15:53

View original

This topic has been closed for comments

2 replies

Userlevel 6
Badge +15

There are few options that i can think of,  if we try this on APP10 or beyond.

  • One WO with multiple Work Tasks each for a given Asset 
  • One Work Task with multiple Work Task steps. each for a given Asset
Userlevel 5
Badge +12

And if we are talking pre APP10 then the only option is the Route-WO functionality. But that requires that the WO is generated from a Route-PM.