@TTRACY ,
How many lines are you referring?
One way is as follow:
- Go to Work Task Time Reports and search for the relevant lines
- Make sure you revoke all authorizations
- After that you need to make a small change on the time report lines and save them. Make sure this is a change which will not affect the lines.
- Then go to Work Task Transactions and search for the relevant lines
- Select all the Cost lines and press ‘Check and update Accounting’, this will check the correct cost on that specific date of the time report.
Unfortunately step 3 is needed, I was not able to manage this without this step. My suggestion would be to change the comment field.
Hope you will manage,