Hi all.
I’m trying to set a up a resource break but how can I change to schedule?
I already recalculated the resource, opened in MPB but it still let me schedule the resource during this time.
tks
Hi all.
I’m trying to set a up a resource break but how can I change to schedule?
I already recalculated the resource, opened in MPB but it still let me schedule the resource during this time.
tks
Hi, I could get it.
I need to schedule the break inside MPB before schedule the work task.
Tks for attention!!