Is is possible to générate maintenance plan with earliest date 15j before due date ? 

the line is uopdatable manueally but we would like to have it automatically 15j before due date.

and lastest finish = due date
 

does it need Event ? or a parameter coud allow that ? 

 

Regards

Hi,

 

You can try below options in PM Action > Maintenance triggers tab.

 

Under planning window information:

 

Expand backward: The duration Earliest Start is to be extended from the Due Date in the maintenance plan. If a value is set to this field, Earliest Start = Due Date - Expand Backwards. When assigning a value to this field it is important to consider the Interval and the Expand Forward values of the PM action to avoid overlapping maintenance plan lines.

 

Expand forward: The duration Latest Finish is to be extended from the Due Date in the maintenance plan. If a value is set to this field, Latest Finish = Due Date + Expand Forward. When assigning a value to this field it is important to consider the Interval and the Expand Backward values of the PM action to avoid overlapping maintenance plan lines.

 

 

Kindly check whether this helps.

Best Regards,

Thilini


hi

I don’t have this option (i’m on 21r2). It it available on 22r1 or more ? 
 

version
 

Best regards


Hi,

I’m afraid this is a new functionality and it is not available in 21R2 version. But it is available in 22R1 and 22R2 versions (and onwards).

For example I checked in:

 

22R1:

IFS Aurena framework version: 22.1.13.20230301085401.0

IFS Aurena client version: 22.1.13.20230301085401.0

IFS OData provider version: 22.1.13.20230301160126.0

 

22R2:

IFS Cloud Web version: 22.2.6.20230310132734.0

IFS OData provider version: 22.2.6.20230302030256.0

 

Best Regards,

Thilini


Thanks