Within the PM Action, the Last Work Task Completion Date is incorrect causing the rest of the Maintenance Plan to be scheduled incorrectly.
The Work Task was initially closed down with the incorrect Actual Finish Date which is what has pulled into the Last Work Task Completion Date.
Reopening the Work Order and Amending the Actual Finish Date is not working. How do i resolve this?