Question

Performed Value Based for multiple PM Triggers

  • 7 August 2023
  • 1 reply
  • 62 views

Userlevel 5
Badge +13

​Hi All,

I want to know your opinion on the field ‘performed value based’ in PM Actions. Please consider the following scenario:

I have one PM action with two Maintenance triggers:

  1. On a bad condition (new in 23R1)
  2. Every 100 hours (with performed value based TRUE)

Now we have a situation where we record a bad condition at 125 hours, so trigger 1 has created a work order and work task. At completion of this work task, the hours are 135 hours.

What do you expect in the maintenance plan for trigger 2? My opinion is that the next trigger will be set to 235 hours, but that is not the case, it remains at 100 hours. It is only taking the hours on work of trigger 2 and not the other triggers.

See PM Action:


With a maintenance plan:


Based on trigger 1 a work task is created and completed. Just before completion of the work task a new reading is set for the hours to 135. I would like that the Maintenance plan for the accumulated triggers is updated. It should not check why the Work is generated.

 

All thought will be appreciated,

Thanks,

Robert


1 reply

Userlevel 2
Badge +6

@EqeRobertK I agree with you. The PM plan should consider all parameters as it has in the past. Have you tried mixing other params? I wonder if the PM plan might be broken.