Solved

Maintenance Plan for Separate PM Action Apps9

  • 8 August 2023
  • 2 replies
  • 71 views

Userlevel 2
Badge +4

Hello Community, 

I created a Separate PM Action, but I can’t figure out how to get IFS to create the Maintenance Plan.  I was able to Manually Generate a Work Order, but I would like to see the plan at lest for the year.  You can see my Maintenance Plan parameters on the attachment.  Please help! 

icon

Best answer by CindyH 8 August 2023, 18:55

View original

2 replies

Userlevel 2
Badge +6

Navigate to Maintenance plan in IFS and then extend/shorten plan. You may have to set it out further into the future. You will have to remember to do this every so often. I am on a later version so no screenshot. 

See this post 

 

Userlevel 2
Badge +4

Thank you! 

That fixed my issue!!

Reply