In IFS Cloud 23R2, we have a scenario to create condition-based PM action to generate Work Orders for objects based on run hours. We are using Accumulated parameter for this scenario. When we update either the ‘New Reading Value’ or the ‘New Delta Value’, the last recorded value is not updated automatically. When we regenerate the plan, it sometimes gets updated and sometimes it does not update. The ‘Plan out of sync’ is set to True in this scenario and doesn’t allow to generate the work order. 

Do we need to Regenerate the Plan every time a measurement is entered for an object? Is there a reason, even after regenerating the last measurement value is not being updated? Any inputs would be appreciated.

Thank you!

 

Hi,

When a measurement is entered, the system create the PM plan regeneration as a background job. This is to avoids adding PM regeneration time to the measurement entry process, as measurement entry expects for a quick response time. Until that background job executes, the plan will remain “out of sync”. Alternatively, users can manually trigger the PM regeneration, like you do, if immediate syncing is needed. But overall, there is an automatic process in place to take care of it eventually
 

BR,

Dilani


Hi ​@Dilani, thank you for the response. Yes, there is a background job but it errors out mostly with the error message ‘This background job was set to state Error because the executing Oracle process was killed’. Even when I try to re-execute the job, it times out. What causes this issue and is there a workaround to execute the background job? Please let me know.


Reply