With related to Depreciation post above Customers are no longer possible to schedule resources for for Work Order connected work task using dispatch console. In previous releases it also depreciation Allocate resource Gantt. Now customers only have Assigned work to plan resources. For customers with considerable amount of maintenance staff it’s difficult to plan without visible support of technicians schedule.
For Resource planning and assignments in maintenance will there be coming a new solution for this?
Depreciation of Service capabilities in WO