Hi,
Is it possible to disable below pop up when fulfilling a Activity on service order and duration not match completeion time minus Start Time?

We on 15.3.05
Thanks.
Robin
Hi,
Is it possible to disable below pop up when fulfilling a Activity on service order and duration not match completeion time minus Start Time?

We on 15.3.05
Thanks.
Robin
Best answer by Phil Seifert
Hi Robin,
Be aware that it also recalculates the duration based on whether you changed the start or end time of the labor activity so it is not just prices involved. Duration of course affects pricing but I am concerned you may do reporting on actual time spent for financial profitability.
Change duration, it will recalculate (or attempt to) adjust the end time of the activity if that is not in the future.
Change the start or end time, it will recalculate the duration.
If you are reporting on how much effort your agents took (duration) for labor costing, not having this pop-up will cause the duration not to align with the actual recorded times.