Hi,
We experience an issue when we try to complete a project. We want to complete a project for 100%.
When I run the ‘Generate Unfinished Work Activity Items' event in the Project Deliverables Navigator, I get the following result:

I cannot set the status of the project to Completed because there are some supplier invoices which we have not received. So when I try to complete the project in the finance module, I cannot complete it for 100% because the status of the project is not Completed (and this is blocked by the supplier invoices which we have not received yet). The screenshot below shows the error in the finance module.

Is there a way to work around this issue? We want to complete the project for 100% and we do not want to wait on our suppliers for sending the invoices.
We are on APPS10 Update 7.