We have a problem with Shop Order requisition due dates relative to shop order start dates that result from a MRP run. If our order quantity is 1, the manufacturing lead-time is 5, and the due date is 09/25/2020 then the start date will be 09/24/2020; why is it not offset 5 days? Should be offset by the fixed manufacturing lead-time. If we change the order quantity to 10, then the start date is offset by 10 days and is 9/15/2020; this is not good. We want to use “standard practice” where the lead-time offset is not affected by the order quantity size.
Can anyone please help with this?
EDM