Hi Lucie,
In IFS standard functionality you can link an Expense to a Project Activity or a Work Task. What customers would commonly do to solve this requirement is to setup Project Activity/Activities for Training and have the Employee report Training Expenses towards those Project Activities, which in turn are linked to a relevant cost center.
It would however not be possible for the Training Coordinator to only Approve the Training Expenses without a configuration/modification. It would be possible with a manual routine where the Training Coordinator only handle the Training Expenses and the Manager handles the other expenses. The Training Coordinator would however still see all the Expenses, not only the ones for training, and I assume that would not be desired?
I would however want to ask why the Training Coordinator should be the one approving the Training Expenses? Would the Manager not be the one approving which Training the Employee should attend? In that case I also think the Manager should approve the Training Cost. Especially if the Training requires traveling and other costs in order to obtain the Training.
Regards,
Magnus